How to set up a concrete pump on site: ground and outriggers

Most serious boom pump accidents start at set-up. A step-by-step guide to ground selection, outriggers, checking the surroundings and communication.

Beton pompası sahada nasıl kurulur? Zemin ve destek ayakları

A boom pump is one of the most impressive machines on site. Behind that impressive sight lies a big responsibility: when the boom unfolds, the whole weight rests on the ground under a few outriggers. If set-up is not done right, even the best-maintained pump becomes a risk.

1. Read the ground

The outriggers must stand on firm, level ground. Freshly filled soil, excavation edges, covered channels and manhole covers may look solid at first sight but can settle under load. If you are unsure about the ground, decide together with the site supervisor.

2. Extend the outriggers fully

Outriggers must be extended as shown in the manufacturer’s instructions. “It’s a short pour today, half-way will do” is one of the most dangerous shortcuts. Placing sufficiently large support pads under the outriggers spreads the load over a wider area.

3. Level the vehicle

The boom must not be unfolded before the vehicle is level. If required, the wheels are relieved of load. A set-up on sloping ground changes the balance as the boom moves.

4. Check the surroundings

  • Safe distance to power lines
  • Conflicts with buildings, scaffolding and cranes
  • The area where truck mixers will approach the pump
  • Pedestrian and worker traffic

5. Agree communication in advance

Hand signals or a radio channel between the operator, the hose worker and the mixer driver must be agreed before pouring starts. Sudden movements of the end hose are a serious risk for anyone standing off-balance at the hose end.

What to watch during pouring

The ground under the outriggers must be watched throughout the pour; stop at the slightest settlement. Signs of a blockage in the pipeline must also be followed closely; our pipeline blockage guide helps here. For the start and end of the day, see our pump start-up and cleaning guide.

The equipment itself is part of safety

However well the set-up is done, a worn pipe or damaged clamp is a risk under pressure. For pipes, elbows and clamps, hydraulic cylinders and hydraulic control parts, see our concrete pump spare parts.

Safety: Set-up and operation must be done only by a trained operator, in line with the manufacturer’s instructions and safety regulations.

Frequently asked questions

Why must concrete pump outriggers be fully extended?

When the boom unfolds, the load is carried to the ground through the outriggers. If they are not fully extended the balance can be lost, so extend them as shown in the manufacturer’s instructions.

Why are pads placed under the outriggers?

Support pads spread the load over a wider area and reduce the risk of the ground settling.

Published:

Ulmet Technical Team
Written by Ulmet Technical Team

Ulmet’s engineering and after-sales team. We write guides on using, maintaining and repairing truck mixer, concrete pump and silo equipment.

Let’s find the part you need.

A part name, part number or photo is enough. We will send you price and lead time as soon as possible.

WhatsApp Request a Quote